Jawa Barat
Interpretation Safeguard
Local generation is not total available supply. Electricity may enter or leave a region through interconnected systems. The regional accounting difference compares where electricity is generated with where electricity is distributed; it is not an operational adequacy, reserve-margin, shortage, or blackout indicator.
Distributed Electricity and Local Generation (GWh)
Annual values for 2011–2030 · straight segments preserve annual observations · forecast horizon is shaded
Regional Accounting Difference (GWh)
Local generation minus distributed electricity · positive or negative values are accounting differences, not operational surplus or shortage
Forecast 2025–2030
All electricity values are in GWh · Distributed electricity model: Drift · Local generation model: Drift V1
| Year | Distributed | Local Generation | Difference | Difference % |
|---|---|---|---|---|
| 2025 | 63.8k | 46.6k | −17.2k | -27.0% |
| 2026 | 65.9k | 48.7k | −17.1k | -26.0% |
| 2027 | 68.0k | 50.9k | −17.1k | -25.1% |
| 2028 | 70.1k | 53.1k | −17.0k | -24.3% |
| 2029 | 72.2k | 55.3k | −17.0k | -23.5% |
| 2030 | 74.4k | 57.4k | −16.9k | -22.8% |
Historical Availability and Geography Notes
Missing historical values remain blank and are never converted to zero.
Interpolated targets support continuity and are explicitly identified as interpolated.
These years are excluded when historical administrative geography is not comparable.